A building visible on the aerial survey of 21 June 2011 can be legalised, with no application deadline. The application through eDozvola needs an as built survey, a structural statement and a geodetic survey, and a fee is paid before the decision.

Guide · Updated

1. The building must appear on the aerial survey of 21 June 2011

A building can be legalised if it is visible on the DOF5/2011 digital orthophoto map, flown from 21 June 2011. At least the rough structure of one storey must show: foundations with walls, or columns with beams and a floor slab or roof structure. The same applies to an extension or an added floor on an existing building.

If the building is not clearly visible on that image, another orthophoto map of the State Geodetic Administration flown before 21 June 2011, or an entry on the cadastral plan by that date, can serve as proof. A certificate from the cadastre is then attached. Anything built later cannot be legalised.

2. We check whether the building can be legalised where it stands

A building can be legalised even if it does not comply with the spatial plan, but then with at most two storeys, the upper one an attic, unless the town or municipality has allowed more by decision. Where the plan sets no number of storeys, at most four can be legalised.

Some locations rule legalisation out. Before you pay for any documentation, we check the plan for your plot and tell you honestly what is possible. The check takes up to one week.

Legalisation is not possible, among other cases

  1. 01in corridors of planned roads and other infrastructure
  2. 02on land zoned for public and social use, unless the building serves that use
  3. 03on maritime domain and in UNESCO world heritage areas
  4. 04for a building on the boundary with a window, door, balcony or projection facing the neighbouring building plot
  5. 05for containers, prefabricated cabins, sheds and similar structures

Some defects can be removed before the decision, for example by closing an opening on the boundary or removing a storey. The building can then be legalised.

3. As built survey and structural statement

The as built survey is prepared by a licensed architect or licensed civil engineer. We come to the site, measure the building and draw it as it actually stands. Depending on the size of the building this takes two to four weeks.

For a finished building a licensed civil engineer also states that it meets the requirement of mechanical resistance and stability. The survey can include an outbuilding next to the main building.

The as built survey contains

  • Details of the owner and the designer
  • Location: address, cadastral plot and municipality
  • Architectural description and description of installations
  • Floor areas, number of storeys and building height
  • Plans, sections and elevations
  • At least four photographs showing every elevation
  • Degree of completion and data for calculating the fee

For an outbuilding of one storey with a footprint up to 50 m² that serves a legal main building, an extract from the digital cadastral plan and proof that the main building is legal are enough.

4. A land surveyor records the building on the plot

The application includes a geodetic survey of the building: its corner points in GML format, prepared by a licensed geodetic engineer. If the building is already drawn on the cadastral plan, an extract from the digital cadastral plan is attached instead.

The geodetic survey and the as built survey are prepared electronically and signed with an electronic signature. We coordinate the measurements with the surveyor so both documents show the same building.

5. Application through eDozvola, site visit and fee

The application goes to the building authority through eDozvola, with all attachments. An application without them is treated as not filed. There is no deadline. The authority checks the 2011 image, visits the site and invites the owners of neighbouring plots to inspect the file through the electronic notice board, for eight days.

Before the decision a fee for keeping the building is paid. The town or municipality sets the amount by decision, under a government decree, depending on the size, location and use of the building. An amount above 500 € can be paid in instalments.

If a court dispute over the ownership of the building or land was started before the application, the procedure is suspended until it ends, when a party raises and proves it.

6. The legalisation decision and registering the building

A finished building with a legalisation decision counts as a building with a building permit and a use permit. It can be used, connected to utilities, reconstructed and divided into flats. An unfinished building can be completed without a new permit, within the legalised size and under a main design.

Once the decision is enforceable, the utility contribution (komunalni doprinos) is paid, except for an outbuilding. The cadastre records the building and sends the decision to the court for the land register itself. The decision does not change ownership of the building or the land.

Common questions about legalisation

Is there a deadline for legalisation?

No. An amendment in force since 16 May 2026 removed the application deadline. The 21 June 2011 limit for when the building was built still applies.

Source · Amendments NN 48/2026, čl. 5 ↗

How much does legalisation cost?

The cost has several parts: the as built survey with the structural statement, the geodetic survey, the fee for keeping the building and, after the decision, the utility contribution. The fee and the contribution are calculated by the town or municipality and depend on the size, location and use of the building. We quote for our part after the check.

Source · Zakon o postupanju s nezakonito izgrađenim zgradama (Illegally Built Buildings Act), čl. 22, 25 and 27 ↗

My application was refused before. Can I apply again?

After a final refusal a new procedure is not possible. The exception is applications refused under the old act because the required documents were missing or the fee was not paid: those can be filed again.

Source · Amendments NN 48/2026, čl. 5 and 26 ↗

What if a neighbour objects?

A neighbour is a party to the procedure and can inspect the file. The decision can be issued even if they do not respond. The procedure is suspended only if a court dispute over ownership of the building or land was started before the application.

Source · Zakon o postupanju s nezakonito izgrađenim zgradama (Illegally Built Buildings Act), čl. 17 and 19 ↗

Do you handle legalisation anywhere in Croatia?

We take on legalisation in Slavonski Brod and the surrounding area. We measure the building on site ourselves for the as built survey, so places further away are not practical for us.

I live abroad. Do I need to come to Croatia?

Someone has to give access to the building for measuring and the site visit. We handle the rest of the procedure, and you sign only what is necessary.